The owner obligations MBIE lists, turned into records you can tick after the work is done.

MBIE lists what a building owner must do when a compliance schedule exists. The short version is: keep the schedule, have the stated procedures carried out, engage IQPs, collect Form 12A certificates, supply a BWoF to the council on each anniversary, display it, and keep inspection records for at least two years with the schedule. The long version is on https://www.building.govt.nz/managing-buildings/managing-your-bwof

This checklist follows that page. It does not add duties. FireCert Clock does not decide that your building needs a compliance schedule. The council does, when consented work includes specified systems, or when you apply because a schedule was never issued.

Owner records

  • Compliance schedule issue date, and the place the schedule is held.
  • For the first 12 months, the compliance schedule statement the territorial authority issued, displayed in the building. After that, the BWoF takes the public display role. MBIE describes both.
  • Every specified system, copied from the compliance schedule.
  • The performance standard and the inspection procedure the schedule already states. If you need a different frequency, that is a schedule amendment the council considers. Do not silently change the legal procedure in a notes field and treat it as done.
  • An IQP for each system, chosen from the council register, with name, credential, and contact.
  • Inspection frequency you are tracking: weekly, monthly, six monthly, or annual. You set it to match the schedule.
  • Form 12A received: yes or no, and the date. Open the missing 12As view before you prepare Form 12.
  • Form 12 details MBIE says the warrant includes: location, lawfully established use and occupant numbers where there is more than one use, owner, original construction date, and the highest fire risk category where it applies.
  • Council submission date, separate from the anniversary you confirmed.
  • Public display: a copy where users of the building can see it, such as the ground floor, lobby, entry, or reception. The checkbox records that you displayed it.
  • Reports of inspections, faults, and repairs kept for at least two years, with dates, work, faults, remedies, and the person who did the work. MBIE says those reports sit with the compliance schedule. They are not Form 12A.

Fines are maximums

For specified BWoF offences, section 108 of the Building Act 2004 sets maximum fines of up to NZD 50,000 for an individual and up to NZD 150,000 for a body corporate: https://www.legislation.govt.nz/act/public/2004/0072/207.0/DLM306869.html

Read the section before you treat a number as the penalty in a real case.

The form split is Form 12 vs Form 12A. The anniversary steps are BWoF renewal process.

Upload your last warrant and we fill it in for you

Upload the compliance schedule or the last warrant and review the suggested checklist fields. The steps are on upload a building warrant of fitness.

Owner checklist, tied to the sources read on 9 Nov 2026

MBIE's owner page and the November 2010 booklet, read 9 Nov 2026, describe the same sequence. Use the current page for the duty and treat the booklet's dollar fines as dated. https://www.building.govt.nz/managing-buildings/managing-your-bwof

FeatureStepEvidenceTracker
ScheduleHold a compliance schedule if the building has specified systemsThe schedule, naming performance standards and proceduresIssue date stored. No extra countdown
First yearDisplay the compliance schedule statement for the first 12 monthsThe statement in a public placeDo not force Form 12 into that first year
InspectionIndependent qualified persons carry out the procedures at the schedule frequencyOn site log and reportsOne line per system, frequency from the schedule
CertificatesForm 12A for every specified system, before the warrantThe certificates, unalteredReceived flag per system
WarrantSign Form 12 on the anniversary, display it, supply it to the council with the certificates and any amendment recommendationsSigned form and proof it was suppliedConfirmed anniversary
KeepCompliance schedule at the stated location, and the Form 12As for the life of the building as the booklet saysThe file locationUpload copies. Paper location still matters
AmendTell the independent qualified person if the schedule changes. The handbook says the anniversary does not moveThe amended scheduleSame anniversary, updated procedures

How to track the list across a portfolio

One site per compliance schedule. Confirm the anniversary only after the Form 12A set is complete if your process is "we do not supply an incomplete warrant". If you want the overdue list to show the approaching anniversary while certificates are still arriving, confirm the date and keep the missing certificates as open system rows. Say which of those two habits you use, and do not mix them inside one account without a note. Upload on upload a BWoF.

Form differences are on Form 12 and Form 12A. The renewal narrative is renewal.

Specified systems MBIE describes include fire separations and emergency systems among others. The schedule for your building is the list that counts, not a generic catalogue.

What if an independent qualified person recommends an amendment?

Form 12 has a place for those recommendations. Supply them with the warrant. The handbook says an amendment can proceed after consultation with the owner, and in some cases without the owner's agreement. The anniversary stays. Update your lines when the council issues the amendment.

Does a public display in the management office count?

The booklet says a place building users can see, and gives the lobby, entry foyer, or reception as examples. An office the public cannot enter does not match that description. Record the actual place.

Before you supply the copy to the council

Count the specified systems on the compliance schedule and count the systems named across the Form 12A set. The numbers need to match, or the handbook's rule that the certificates together cover every system is not met. Check the display location against the examples MBIE gives: lobby, entry foyer, or reception, not a locked office. Check that Form 12 states the same location where the schedule is kept. Then supply the warrant, the certificates, and any amendment recommendations. Confirm the date in the tracker after that supply, and keep the council's acknowledgement with the upload. A confirmed date without that acknowledgement is only your intention.

FAQ

Does the first year use a BWoF on display?

MBIE says the compliance schedule statement is displayed for the first 12 months. The BWoF is what you display after that, until the next anniversary.

Can the tracker amend the compliance schedule?

No. Recommendations for an amendment can be attached to the BWoF you send the council. The council decides whether the schedule changes.

How long are inspection reports kept?

MBIE says at least two years after they are issued, with the compliance schedule. The activity CSV is an extra export of what you confirmed in the product, not a replacement for those reports.

Track your BWoF dates free