The permit or the determination names the measures and how often they are maintained. You type those intervals.
Regulation 194 of the Building Regulations 2018 (Vic) says an occupancy permit must specify the essential safety measures and the related requirements where the Part 15 rules apply to that permit. Those requirements include the level of performance the measure must achieve and the frequency and type of inspection, testing, and maintenance. The regulations are published at https://www.legislation.vic.gov.au/in-force/statutory-rules/building-regulations-2018
A maintenance determination under regulation 215 is a different document. The note is maintenance determination for essential safety measures in Victoria. The Victorian Building Authority publishes a form for it: https://www.vba.vic.gov.au/building/building-resource-hub/building-forms
Regulation 218 to 222 cover maintenance schedules for an existing building or place of public entertainment, including an owner application and the surveyor's duty to give the owner a copy. A schedule is not the same document as a determination. Keep the one the building actually has.
What to type, and what not to invent
The occupancy permit row and the maintenance determination row start with no proposed due date. A permit is not renewed on a statewide anniversary by this product. If your building has a condition that sets a review, type that confirmed date yourself.
For each measure named on the permit, determination, or schedule, add an essential safety measure line. Set the inspection frequency to the word that matches the document: weekly, monthly, six monthly, or annual. If the document uses a different gap, leave the frequency unset and write the gap in the notes. Do not copy an NFPA interval onto a Victorian measure because it looks familiar.
The VBA guide says that for buildings constructed or altered since 1 July 1994, the list of measures, including performance level, frequency, and type of maintenance, is included with the occupancy permit or certificate of final inspection. For buildings built before 1 July 1994, the owner still maintains safety equipment, safety fittings, and safety measures so they fulfil their purpose, including exits and paths of travel. That guide is https://www.vba.vic.gov.au/consumers/guides/essential-safety-measures
Regulation 196 says that, in the cases it describes, compliance with AS 1851-2012 is taken to be compliance with an earlier standard named for a measure. Regulation 217 says the same kind of thing for a maintenance determination. If you are on that path, the annual report has to say so. Ask the person who maintains the measure before you tick anything. The standard is not hosted here.
Display of the occupancy permit is regulation 197, for the buildings that regulation covers. The profile checkbox is a note that someone checked the display. It is not the display.
Upload the permit and we fill it in for you
Upload the occupancy permit or the maintenance determination and review the suggested measure names and the frequencies written on it. The steps are on upload a Victorian ESM report.
The annual report clock is separate and is explained on VIC ESM annual report date. Owner duties are on VIC ESM owner obligations. The overview is Victorian essential safety measures. That overview is essential safety measures in Victoria. Melbourne owners start from essential safety measures melbourne. The yearly file is the AESMR.
Presets are a guide. Confirm the measures with the municipal building surveyor or a qualified practitioner. The document issued for the building takes precedence. FireCert Clock does not certify a measure.
What the permit lists, and what it does not renew
Regulation 194 of the authorised Building Regulations 2018, read 9 Nov 2026, says the relevant building surveyor or the Authority must ensure an occupancy permit specifies all essential safety measures required as part of the building work, and the level of performance each measure must achieve. That list is the maintenance program for those measures. It is not a date that comes around by itself. https://content.legislation.vic.gov.au/sites/default/files/6c6863f2-b399-3ca2-9d3e-2fc9f014c810_18-038sra%20authorised.pdf
Regulation 197 in that text requires the owner to display a current occupancy permit for Class 1b, 2, 3, 5, 6, 7 and 8 buildings constructed on or after 1 July 1994, for Class 9 buildings, and for places of public entertainment. The stated penalty is 10 penalty units. Regulation 199 says a copy is available for inspection by the municipal building surveyor or chief officer on request, with the same stated penalty. The commission guide, read 9 Nov 2026, describes display in a prominent position, including a framed copy or a sealed notice board, and says multiple pages may be laminated. https://www.vba.vic.gov.au/consumers/guides/essential-safety-measures
The guide also says that for buildings constructed or altered since 1 July 1994, the frequency and type of maintenance are included with the occupancy permit or the certificate of final inspection. Type those frequencies onto schedule lines. There is no statewide frequency table in the product.
Permit versus determination versus report
| Feature | Occupancy permit | Maintenance determination | Annual report |
|---|---|---|---|
| Creates the measure list | Yes, for the work it covers | Yes, where regulation 215 is used | No. It reports on measures already required |
| Renewal | None statewide | None statewide | Every anniversary, inside the 28 days before it |
| Display | Regulation 197, for the classes it names | Not a display duty in the sections read | Keep it for the 24 hour inspection under regulation 225 |
| What you store | The permit, the list, the performance levels | The determination and its frequencies | The signed report and the anniversary you confirm |
How to track the list
Open the permit once. Add a line per measure with the frequency printed on it. Do not add a countdown to the permit row. Put the countdown on the annual report, using the anniversary from annual report date. Upload the permit or the report on upload a VIC report. If a later alteration changes the permit, update the lines. The product will not notice the alteration until you do.
Owner duties that sit beside the permit are on owner obligations. Frequencies written by the surveyor are on the maintenance determination.
What if the building has a certificate of final inspection instead of a permit?
The guide says the list can come with the occupancy permit or the certificate of final inspection for work since 1 July 1994. Store the document you actually hold. Do not rename it as a permit if it is not one.
Does display of the permit satisfy the annual report?
No. They are different regulations. A permit on the wall does not prepare regulation 223's report.
FAQ
Can I load every Schedule 8 item onto every building?
No. Schedule 8 is the definition list. The rows you track are the measures the occupancy permit, maintenance determination, or maintenance schedule actually names for that building.
Who prepares a maintenance determination?
Regulation 215 sets out when a maintenance determination is made. The product stores a copy and a date you confirm. It does not issue the determination.
What if the certificate of final inspection lists the measures instead of an occupancy permit?