Keep the annual report anniversary, the occupancy permit, and the maintenance determination on one building, and confirm the date before any reminder starts.

The owner duties that follow from the definition below are the maintenance, the annual report, and the records an owner keeps. FireCert Clock stores the dates you confirm. It does not write the report, sign it, or give it to a municipal building surveyor.

The regulations came into operation on 2 June 2018. The in force instrument is on legislation.vic.gov.au: https://www.legislation.vic.gov.au/in-force/statutory-rules/building-regulations-2018

Presets are a guide. Confirm the dates and the measures with your council or a qualified practitioner. Your occupancy permit, maintenance determination, or maintenance schedule takes precedence. This is not a government service.

What essential safety measures are

Essential safety measures are the safety features the owner of a Victorian building, other than a house or an outbuilding, is responsible for keeping working. The Building and Plumbing Commission says the term is defined in Part 15 of the Building Regulations 2018 and includes items listed in Schedule 8, such as emergency warning systems, fire extinguishers, fire hydrants, paths of travel to exits, smoke alarms, and smoke control systems. Regulation 214, in Part 15 Division 1 of the version 032 authorised text, is that definition: a Schedule 8 measure required for the building, an item the relevant building surveyor designates for the safety of persons in the event of fire, and the earlier measures the regulation still carries. Guide: https://www.vba.vic.gov.au/consumers/guides/essential-safety-measures Version 032 PDF, read 17 Nov 2026: https://content.legislation.vic.gov.au/sites/default/files/2026-10/18-38sra032-authorised.pdf

Annual Essential Safety Measures Report (AESMR)

Regulation 223 requires the owner to ensure an annual essential safety measures report is prepared, in line with regulation 224, within 28 days before the anniversary. Regulation 224 says that report is in a form approved by the Authority and is signed by the owner, with the date rule on the Annual Essential Safety Measures Report (AESMR), also called the annual essential safety measures report and aesmr.

What the building profile keeps

The annual report is the dated row. Regulation 223 says the owner must ensure an annual essential safety measures report is prepared, in line with regulation 224, within 28 days before each anniversary of the relevant anniversary date. Where an occupancy permit or a maintenance determination required the measure, that anniversary is the earlier of two dates: the first occupancy permit, or an amendment to it, that required the measure, and the first maintenance determination that required it. For a building constructed before 1 July 1994 that is covered only by regulation 223(2), the report is prepared within 28 days before 13 June 2018 and each anniversary of that date. Regulation 223(3) says the 13 June rule does not apply to a measure that already needs a report under regulation 223(1).

Type that anniversary. The preset proposes the same calendar day 12 months later, with 29 February clamped to 28 February in a non leap year. You confirm the date or replace it. Reminders use only the confirmed date.

The occupancy permit row and the maintenance determination row do not propose a date. Regulation 194 says an occupancy permit must specify the essential safety measures and the related requirements where that permit applies. Regulation 215 is the maintenance determination, and regulation 216 says the owner must comply with it. The frequency for each measure is written on those documents. Add a schedule line for each measure and set weekly, monthly, six monthly, or annual yourself. There is no statewide interval table in this product.

Regulation 224 says the report is in a form approved by the Authority, signed by the owner, states the address, and states that the owner has taken all reasonable steps to keep each measure operating and maintained. If regulation 196 or 217 applies, the report states that the owner is complying with AS 1851-2012 instead of an earlier frequency named on the permit or determination. FireCert Clock names that standard. It does not reproduce it. The Victorian Building Authority publishes the annual report form and the maintenance determination form: https://www.vba.vic.gov.au/building/building-resource-hub/building-forms

Regulation 225 says the owner must make annual reports from the previous 10 years, maintenance schedules, maintenance determinations, and inspection records available at the building within 24 hours after a request by the municipal building surveyor or chief officer. A file or a link on the report row is your copy of that record. The product does not send it.

Regulation 223 states a penalty of 20 penalty units. That figure is the regulation's penalty, not a quote for a particular building.

Upload the last report and we fill it in for you

Upload the annual essential safety measures report, the occupancy permit, or the maintenance determination as a PDF, photo, or Word file. FireCert Clock suggests the building, the measures, and the dates printed on that file. You accept all suggestions or edit one field. Each suggestion names the file and the page. A confirmed date changes only when you accept that suggestion. Reminders start only on dates you confirm. The steps are on upload a Victorian ESM report.

Related Victorian notes

The anniversary count is on VIC ESM annual report date. Owner duties are on VIC ESM owner obligations. A maintenance determination in Victoria is on maintenance determination for essential safety measures. Read the maintenance determination before you type an interval. The permit and determination rows are on VIC occupancy permit ESM list.

Owners corporations and facility managers can open VIC ESM software for strata. Corporate teams can open VIC fire dates for HSE teams.

Documents and who holds them

The commission guide, read 9 Nov 2026, and the authorised 2018 regulations, read the same day, support this split. Guide: https://www.vba.vic.gov.au/consumers/guides/essential-safety-measures . Regulations PDF: https://content.legislation.vic.gov.au/sites/default/files/6c6863f2-b399-3ca2-9d3e-2fc9f014c810_18-038sra%20authorised.pdf

FeatureAnnual reportOccupancy permitMaintenance determination
AuthorityRegulation 223 and 224Regulation 194 and, for display, regulation 197Regulation 215 and 216
WhoOwner ensures the report. Agent may complete it. Owner signsRelevant building surveyor specifies the measures and performanceOwner complies with the levels and frequencies it sets
WhenWithin 28 days before the anniversary. Pre 1 July 1994 buildings only under regulation 223(2) use the 28 days before 13 JuneNo statewide renewal intervalNo statewide date. The frequency is on the determination
Penalty in the 2018 authorised text20 penalty units on regulation 22310 penalty units on regulation 197 for failing to display where that regulation applies20 penalty units on regulation 216
Tracker behaviourProposes the next anniversary after you type itStores the permit. Does not propose a renewalStores the determination. You type each frequency

legislation.vic.gov.au shows later in force versions, including version 032 on 27 Oct 2026. The penalty units above are from the 2018 authorised PDF, not a claim that no later amendment exists. Check the current consolidation before you quote a fine.

Regulation 225 in that PDF says reports for the previous 10 years and the maintenance schedules must be available within 24 hours of a request by the municipal building surveyor or chief officer.

How to track a Victorian building

Type the anniversary that regulation 223 actually uses for that building. Confirm the proposed date. Add each measure at the frequency written on the permit or determination. Upload the last report on upload a VIC report. The report date note is annual report. Owner duties are owner obligations. The permit list is occupancy permit.

Strata managers: VIC ESM software for strata. HSE teams: VIC fire dates for HSE teams.

Does 13 June override a permit anniversary?

Regulation 223(3) in the 2018 text says the 13 June rule does not apply to a measure that already needs a report under regulation 223(1). Use the permit or determination anniversary for those measures.

Who enforces?

The commission guide says the municipal building surveyor or the chief officer of the fire authority enforces the maintenance provisions, and the council enforces building safety in its municipality. The product enforces nothing.

FAQ

Does FireCert Clock prepare the annual report?

No. You confirm the anniversary, store the records, and use the form the Victorian Building Authority publishes.

Is the proposed date the legal due date?

The preset proposes the next anniversary of the date you type. Regulation 223 places the report in the 28 days before that anniversary. You confirm or edit the date. Reminders follow the confirmed date.

Does every building use 13 June?

No. The 13 June anniversary is regulation 223(2), for a pre 1 July 1994 building that is not already covered by regulation 223(1). If an occupancy permit or maintenance determination sets the anniversary, use that earlier date.