When Is the NSW Annual Fire Safety Statement Due?
Twelve months from the last lodgement is the proposal. The date you confirm is the date the reminders use.
NSW Planning states that an annual fire safety statement must be issued each year and cover the essential fire safety measures that apply to the building. The practical date question for an owner is how long after the last lodgement the next statement has to be in. FireCert Clock treats that window as 12 months from the previous lodgement date, which you type in and then confirm. Source: https://www.planning.nsw.gov.au/the-planning-system/buildings/fire-safety-in-buildings/fire-safety-certification
How the proposal is counted
Enter the last lodgement date. The preset adds 12 calendar months. 1 March 2025 proposes 1 March 2026. 31 January proposes 31 January the next year. 29 February 2024 proposes 28 February 2025, because 2025 is not a leap year and the date is clamped to the last valid day of February. 29 February 2024 plus four years proposes 29 February 2028.
That proposed day is the end of the 12 month window, not a filing. You can confirm it, or type an earlier day when your own program issues the statement sooner. If you type a later day, the product stores it because your schedule overrides the preset. The screen still shows what the preset proposed, so the difference is visible in the activity log.
Reminders do not start until the due date is confirmed. Advance notice uses the days you set, such as 30, 14, 7, and 1, or the thresholds already on the account when you leave that field blank. The email is the existing FireCert Clock reminder, with the item name Annual Fire Safety Statement.
Supplementary dates
A supplementary fire safety statement is issued at the shorter interval the fire safety schedule sets for a critical measure. Add each one as its own line with the statement date and a confirmed next date. Those lines have their own countdown. They do not replace the annual lodgement date.
Upload your last statement and we fill it in for you
If the last lodgement date is already on a PDF or a photo, upload it and review the suggested due date before you confirm it. The steps are on upload an NSW statement.
What this does not decide
The preset does not read your fire safety schedule, does not know which measures are critical, and does not apply a council's late fee. North Sydney Council publishes week by week late fees of AUD 1,000, AUD 2,000, AUD 3,000, and AUD 4,000 on its own page: https://www.northsydney.nsw.gov.au/getting-construction-underway/submit-annual-fire-safety-statement/print
Attribute those figures to that council only. Your council's page is the one that matters for a late lodgement. Sydney council channels and the fees they publish are on lodging in Sydney. The same note is the fire safety statement sydney page. Kiama lodgement is the annual fire safety statement kiama page. The short name afss nsw points at the state guide, and so does fire safety statement.
From 13 February 2026, AS 1851-2012 servicing applies to relevant scheduled buildings. That sentence is a date marker for servicing practice. It does not change the 12 month lodgement count, and the standard is not copied here.
The pillar overview is the annual fire safety statement. Which buildings need one is on which NSW buildings need an annual fire safety statement. That note is what buildings require an annual fire safety statement. The certificate that can move the 12 month test is the NSW fire safety certificate. The field checklist is NSW AFSS requirements.
The later of two 12 month tests
The proposal on this tracker is 12 months from the lodgement date you type. AustLII's consolidation of section 89, read 9 Nov 2026, is more precise than that shortcut. The owner must give the annual statement to the council within the later of 12 months after an annual statement was previously given to the council, or, if a fire safety certificate was issued within the previous 12 months, 12 months after that certificate. https://classic.austlii.edu.au/au/legis/nsw/consol_reg/epaacafsr2021839/s89.html
NSW Planning's certification page, read 9 Nov 2026, still says the annual statement is issued each year. Use the section 89 test when a completion certificate and a previous statement both exist. The product will not pick the later date unless you enter both and confirm the one that applies. https://www.planning.nsw.gov.au/the-planning-system/buildings/fire-safety-in-buildings/fire-safety-certification
Section 88 of the same consolidation, as returned on that read, says a person must not issue the annual statement unless the assessment and inspection were carried out within the previous 3 months. Book the practitioner with that window in mind. The tracker does not count the 3 months for you.
Worked dates, labelled as arithmetic
Last statement given to the council on 14 March 2025, and no fire safety certificate in the previous 12 months. Twelve months later is 14 March 2026. That is the proposal. Confirm it or bring it forward if you issue earlier.
Last statement given on 14 March 2025, and a fire safety certificate issued on 2 November 2025. The later of 14 March 2026 and 2 November 2026 is 2 November 2026. Type 2 November 2026 as the confirmed date. The untouched proposal would have stayed on 14 March and would have been early relative to that test. Early is not the same as wrong, but a board paper should not call 14 March the statutory outer day.
29 February 2024 plus 12 months clamps to 28 February 2025. That clamp is a calendar fix in the product. It is not a clause you should quote as the regulation.
How to track the outer day
Put the council given date in the lodgement field, not the day the practitioner visited, unless those days are the same. Upload the receipt on upload an NSW statement. Add supplementary lines from the schedule. The field list is requirements. The statement contents are what an AFSS includes.
Penalties in the section 89 consolidation read that day: 800 penalty units for a corporation and 400 for an individual for not giving the statement, a separate weekly offence after the time has passed, and 55 penalty units for not displaying the statement and the current schedule. Dollar values of units change. Do not invent them.
What if the council date and the statement date differ?
Track the date section 89 cares about for the next outer day: when the statement was given to the council. Keep the issue date in the notes if your file needs both.
Does a supplementary date move the annual date?
No. The FAQ read on 9 Nov 2026 says supplementary statements follow the schedule interval for critical measures. They do not replace the annual statement.
FAQ
What if the last lodgement was 29 February?
The next proposal in a non leap year is 28 February. In the next leap year the anniversary can fall on 29 February again. Confirm the day you will actually use.
Can I keep a shorter internal date?
Yes. Confirm the earlier date. Reminders follow the confirmed date. The proposal stays on the record so you can see the 12 month mark.
Do reminders go out before I confirm?
No. A proposal alone does not start email. Confirm the due date first.