Victoria Essential Safety Measures Maintenance Determination
Regulation 215 is the determination. Regulation 216 is the owner's duty where no occupancy permit applies. The frequency is the one written on the form.
A maintenance determination in Victoria is a written determination by the relevant building surveyor under regulation 215 of the Building Regulations 2018. It names the essential safety measure, the level of performance that measure must achieve, and the frequency and type of inspection, testing, and maintenance required for it. The in force regulations, version 032, authorised PDF read 13 Nov 2026, are published from https://www.legislation.vic.gov.au/in-force/statutory-rules/building-regulations-2018/032 and the PDF is https://content.legislation.vic.gov.au/sites/default/files/2026-10/18-38sra032-authorised.pdf
Essential safety measures are defined in regulation 214 of that same authorised text. They include a safety measure in column 2 of the tables in Schedule 8 that the Act or the Regulations require, any other item required for the safety of persons in the event of fire that the relevant building surveyor designates, an item that was an essential safety measure under regulation 1202 of the Building Interim Regulations 2017 immediately before that instrument was revoked, and a measure required for the safety of persons in the building or place before 1 July 1994. The Building and Plumbing Commission guide, read 13 Nov 2026, describes the same idea in plain language and lists examples such as exit doors, emergency lighting, fire extinguishers, fire detection and alarm systems, paths of travel to exits, smoke alarms, and sprinkler systems. https://www.vba.vic.gov.au/consumers/guides/essential-safety-measures
FireCert Clock stores the determination you upload and the frequencies you type from it. It does not issue a determination, decide a frequency, or sign the annual report. Presets are a guide. The determination and the occupancy permit for the building take precedence.
When regulation 215 requires a maintenance determination
Regulation 215(1), in the version 032 authorised PDF read 13 Nov 2026, applies if an essential safety measure is required to be provided or altered in a building or place of public entertainment by a building permit that does not require an occupancy permit, or by an emergency order or a building order under Part 8 of the Building Act 1993.
Regulation 215(2) says the relevant building surveyor must determine and specify the essential safety measure that is the subject of the determination, the level of performance that measure must achieve to fulfil its purpose, and the frequency and type of inspection, testing, and maintenance required for it.
Regulation 215(3) says the determination must be in writing in the form approved by the Authority. It must be given to the owner with the certificate of final inspection if the measure is required under a building permit. If the measure is required under an emergency order or a Part 8 building order, it must be given to the owner without delay after it is made, and given to the relevant council with a report under section 120(2)(a) of the Act.
The definition in regulation 214 also keeps an older maintenance determination, one that had that meaning under regulation 1202 of the Building Interim Regulations 2017 immediately before revocation. A form that matches either limb is the determination. A maintenance schedule is a different document. Regulation 214 defines a maintenance schedule as one prepared by the municipal building surveyor or a private building surveyor that complies with regulation 222, or a schedule that had that meaning under the 2017 interim regulations immediately before revocation.
Who complies, and which regulation applies
Regulation 216, read in the version 032 PDF on 13 Nov 2026, applies if a maintenance determination is issued for a building or place of public entertainment to which an occupancy permit does not apply. The owner must ensure that each essential safety measure that is the subject of the determination performs at the level specified to fulfil its purpose, and is inspected, tested, and maintained in accordance with the requirements specified in the determination. The penalty stated on regulation 216 is 20 penalty units.
Where an occupancy permit does apply, regulation 195(2) of the same PDF makes it a condition of that occupancy permit that each essential safety measure specified in the maintenance determination is inspected and tested as the determination specifies, and maintained so that it achieves the level of performance the determination specifies. Regulation 195(1) is the parallel condition for measures specified in the occupancy permit itself under regulation 194. The permit condition and the regulation 216 duty are not interchangeable. Read which document the building actually has.
Regulation 217 says that if a maintenance determination specifies maintenance in accordance with AS 1851-2005, published 5 September 2005, or an equivalent standard published before that date, compliance with AS 1851-2012 is taken to be compliance with the frequency and type of inspection, testing, and maintenance in the determination, where that subregulation applies. If the owner complies with AS 1851-2012 on that basis, regulation 217(3) says the owner must continue to comply with AS 1851-2012 for that measure. The standard is not reprinted here. The determination is the document that says whether regulation 217 is in play.
What the determination does not replace
The annual essential safety measures report is still the owner's yearly report. Regulation 223, as the annual report note explains, is a separate duty. The anniversary can be the date of the first maintenance determination that required a measure, when that date is the earlier relevant anniversary under regulation 223(4). The date rule is on the annual essential safety measures report. The determination itself does not become that report.
Regulation 218 says that if an essential safety measure is specified in an occupancy permit under regulation 194, or in a maintenance determination under regulation 215, the relevant building surveyor must prepare or update a maintenance schedule so that it complies with regulation 222. Regulation 222(1) says that schedule lists all essential safety measures specified in the occupancy permit or the maintenance determination and the maintenance requirements for them. Regulation 221 says the surveyor who prepares or updates that schedule under regulation 218 or 220 must give the owner a copy without delay.
Regulation 219 says the owner may apply to the municipal building surveyor or a private building surveyor for a maintenance schedule that complies with regulation 222. Regulation 220 says the surveyor may prepare it if the owner has applied. Those sections create a schedule. They do not rewrite the frequencies already written on a determination.
Regulation 213 says Division 1 applies to a Class 1b, 2, 3, 5, 6, 7, 8, or 9 building, a Class 4 part of a building, and a place of public entertainment. It does not apply to a smoke alarm installed in a sole occupancy unit in a Class 1b or 2 building or a Class 4 part of a building. The commission guide, read 13 Nov 2026, says essential safety measures apply to all buildings apart from a house or outbuilding, and then lists Class 1b through Class 9 in the National Construction Code sense. Where the guide's house exclusion and regulation 213's class list both matter, read regulation 213 for the division and the guide for the commission's summary.
The guide also says owners of all Class 9 buildings, and Class 2 to 8 buildings constructed or altered since 1 July 1994, must display a current copy of the occupancy permit. That display rule is about the permit, not a substitute for keeping the determination.
Frequencies stay on the determination
Regulation 215(2)(c) requires the surveyor to specify the frequency and type of inspection, testing, and maintenance. The authorised PDF does not print one statewide interval for every measure. A weekly, monthly, six monthly, or annual habit copied from another building is not this determination. Type the frequency the form states for that measure. If the form is silent, the next step is the surveyor or the council, not a guessed gap.
Regulation 226, described on owner duties for essential safety measures in Victoria, is the broader maintenance duty. Regulation 216 is the specific duty to comply with the determination where no occupancy permit applies. Keep both labels. Do not tick one and treat the other as done.
The commission guide, read 13 Nov 2026, says non compliance may result in an infringement notice and a fine, or in prosecution and more substantial fines. It does not print the dollar value of a penalty unit. The 20 penalty units on regulation 216 are the regulation's figure. They are not a dollar quote.
Upload the determination and we fill it in for you
Upload the maintenance determination, the certificate of final inspection that came with it, or the occupancy permit that now carries it as a condition. FireCert Clock suggests the building and the measures printed on that file. You accept all suggestions or edit one field. Each suggestion names the file and the page. A confirmed date changes only when you accept that suggestion. The steps are on upload a Victorian essential safety measures report.
The measure list on a permit is the occupancy permit essential safety measures list. The state overview is essential safety measures in Victoria.
Determination, permit, and schedule
| Feature | Maintenance determination | Occupancy permit condition | Maintenance schedule |
|---|---|---|---|
| Source read 13 Nov 2026 | Regulation 215 and 216. https://content.legislation.vic.gov.au/sites/default/files/2026-10/18-38sra032-authorised.pdf | Regulation 195(2) when a determination is made and a permit applies | Regulation 214, 218, and 222 of the same PDF |
| Who writes it | Relevant building surveyor | The permit already exists. The condition is in the regulation | Municipal or private building surveyor |
| What it states | Measure, performance level, frequency and type of inspection, testing, and maintenance | Inspection, testing, and maintenance as the determination specifies | The measures and the maintenance requirements |
| Owner duty | Regulation 216 where no occupancy permit applies. Penalty stated: 20 penalty units | Comply with the permit condition | Provide documents under regulation 218(3) when asked. Penalty stated there: 10 penalty units |
Can the annual report ignore the determination?
No. Where the determination required the measure, regulation 223 uses that determination in the anniversary test. The report still has its own signature rule. See the annual essential safety measures report date.
Is a schedule the same form as a determination?
No. Regulation 214 defines them separately. A schedule lists measures and maintenance requirements. A determination is the regulation 215 document, in the form approved by the Authority.
FAQ
Does the product choose the inspection frequency?
No. Regulation 215 says the relevant building surveyor specifies the frequency and type. You type that frequency from the determination.
What if an occupancy permit already applies?
Regulation 216 is the duty where an occupancy permit does not apply. Regulation 195(2) makes the determination a condition of the permit where a permit does apply. Read the permit before you treat regulation 216 as the only duty.
Where is the approved form?
Regulation 215(3) says the determination is in the form approved by the Authority. The commission publishes building forms from the resource hub linked on owner duties. The product does not host a substitute form.